Stealing of construction materials has slowed down work on the Sunyani inner city roads project in the Sunyani municipality, being executed by the Sino-Hydro corporation of china.
For the past weeks, the construction company has recorded several thefts, particularly, stealing of chippings at its various sites, thereby slowing down the progress of work on the project.
Madam Justina Owusu Banahene, the Bono regional minister disclosed this in an interview with Sompa FM in Sunyani and warned those engaged in such bad practices to stop.
Accordingly, she said the Bono Regional Coordinating Council (BRCC) had mounted surveillance and appealed to everybody to be on the watch to help apprehend the perpetrators.
The Regional Minister described the situation as disheartening and warned that anybody who might be found wanting would be made to face the full rigours of the law.
Vice president Alhaji Dr Mahamudu Bawumia cut the sod for the work to begin on the 29-kilometre Sunyani town roads in September 2020.
Work on the 30- month project, costing the nation about US$45million commenced in December last year and is expected to be completed in June 2023.
It forms part of the rehabilitation and expansion of major roads across the country being funded under the sinohydro agreement the Akufo - Addo government signed with Sinohydro Corporation and the Chinese government.
About eight major suburbs and a total of 26 communities under these suburbs in the Sunyani Municipality are benefiting from the project.
They include Agyei Ano ( Dr. Berko), Mayfair, Baakoniaba, New town, Berlin Top and Penkwase areas' roads as well as Estate inner link roads.
The project also captures specific roads in the Berekum Municipality, which would also cover rehabilitation and expansion works.
Source: Sompaonline.com/K.Peprah